ISB
Work in Progress
- 
	Continue pre cast and brick work along G line, lines 8 to 17. 
- 
	Continue curtain wall installation at the east side of the building. 
- 
	Continue monitor framing and glass at the north side of the building. 
- 
	Continue last back filling in the east section of the building. 
- 
	Last hydraulic slab pouring in the east side of the building is in progress. 
- 
	Start slab on grade pouring on the north side, and 2” topping, from lines 1 to 7. 
- 
	Start slab on grade pouring from lines 13 to 17, and 2” topping from lines 7 to 17. 
- 
	Start framing for penthouse panels. 
- 
	Start metal enclosure for stairs #3. 
- 
	Start metal framing along north canopy and line A. 
Looking Forward
- 
	Finalize pre cast and brick work along G line, from lines 8 to 17. 
- 
	Continue metal framing work along north canopy and line A. 
- 
	Continue MEP equipment installation in penthouse. 
- 
	Continue slab on grade pouring at the east side of the building. 
- 
	Continue back filling on the east side of the building. 
- 
	Start metal enclosure for stairs #3. 
Williams Hall
Work in Progress
- 
	Continue concrete final painting on the north side of the building. 
- 
	Continue with CW work in tunnel. 
- 
	Start installation of the mechanical curbs in basement. 
- 
	Start installation of the switch gear in electric room. 
Looking Forward
- 
	Finalize final painting concrete. 
- 
	Continue with steam station work in mechanical room. 
- 
	Continue with CW work in tunnel. 
- 
	Continue with plumbing underground work. 